Redan Lane Excavation Timelapse
To go up we need to first go down, excavation took about three months and included excavation of 6,064 cubic metres of beautiful Sydney sandstone transported by 337 truck movements. Our builders, Trescon did a brilliant job working hard through all conditions, with only one day lost to weather.